Common Ground Awarded Contract

Common Ground Trails from Western Australia have been the successful tenderer for the Hammon Park Pump Track. 

Screen Shot 2018-07-16 at 1.32.35 pm.png

About Common Ground

Common Ground Trails was founded by David Willcox. David had a desire to influence the mountain bike trails sector with his professional experience in the architecture and planning industries from which he originates. Common Ground Trails has delivered numerous pump track projects, several of which have been with asphalt and has become one of Australia’s leading expert consultancies. 

Progress & Timelines

Work continues on the Master Plan for the park. The project team is working towards a September construction on the pump track which will be a great start to what will become an amazing recreation asset for Creswick. The timeline for the Pump track is as follows: 

  • Detail Design - July
  • Procurement- August
  • Construction- September

After a meeting with the residents of Moore St it was agreed that a revised plan would be developed that moved the car park away from the Eastern boundary of the park to the Western boundary. It was also agreed that it would be preferable if the entrance and exit to the park would be on the Water Street to minimise traffic and disruption to residents. Addressing these requirements is currently underway.